Home entrance with a blue-gray front door and brick porch steps.

Forestbrook Road Widening: Your Daily Drive Through 2029

October 8, 2026

Over the summer, survey flags and wooden stakes went up along the shoulders of Forestbrook Road between Highway 501 and Dick Pond Road. Most people took them to mean the widening had started. According to the South Carolina Department of Transportation, the crews were clearing utility relocations ahead of the main project, which the agency told WMBF it expects to start in early 2027.

So the bigger disruption is still ahead. Highway 501 northwest toward Conway has slipped past its finish date, which moves its last stage of work into the same months the Forestbrook Road widening is set to begin. For anyone who drives out of Forestbrook every morning, early 2027 is the season both main routes out are under work at the same time.

What the Stakes Along the Shoulder Actually Mark

The widening runs in three phases, and each one looks different from the driver's seat. WBTW laid out the order in September 2025 as the county got ready to take bids.

  1. Clearing and grubbing. Trees and brush come out of the future roadway. SCDOT opened bids on December 9, 2025 for Forestbrook Road Widening Phase I, and Seed Slingers LLC was the apparent low bidder at $5,698,496.94. Horry County's project page lists the target for finishing this clearing contract as "Winter 2026."
  2. Utility relocation. Power, water and communication lines move out of the way of the new lanes. SCDOT said in July that this was the stage underway, and it explains the flags and stakes.
  3. Construction. This is the actual widening, expected to start in early 2027. No contractor for this phase has been publicly named in the coverage to date.

At the same time, the county's road-project dashboard lists Forestbrook Road under "Right of Way Acquisition." That's the step where land along the corridor is bought for the wider road. It's also why some news coverage calls the road "under construction" while SCDOT describes it as getting ready to begin. In September, the Sun News's roundup of Horry County road projects listed Forestbrook Road as under construction, with completion expected in 2029. Both descriptions fit the same stretch of pavement, but the lane-by-lane rebuilding hasn't started.

A Quarter of the Budget Spent Before the Main Construction

Horry County lists a budget of $89.1 million for the project, and $22,967,867 had been spent as of the latest update. That's about 26 percent of the money, spent before the main construction contract has started.

With the project still in right-of-way acquisition, clearing and utility relocation, that spending has gone into getting the corridor ready rather than adding lanes. On Forestbrook Road, that preparation also reaches people's land. A property owner told WMBF the widening will take two acres of her land and split the property with a road.

"Growth is inevitable, and we definitely need infrastructural improvements, but it should not come at the expense of the families and farms that built this community." The property owner, speaking to WMBF in July 2026

The total cost isn't settled yet either. In September 2025, WMBF reported an anticipated total cost of $110 million. The county's own page still shows $89.1 million. Neither source explains the roughly $21 million gap. The 2029 completion date has stayed the same in coverage from both years.

Early 2027, When Both Routes Are Under Work

The Forestbrook Road calendar would be simple to plan around on its own. The problem is that Highway 501 is running late.

The Highway 501 widening between Highway 544 and Myrtle Ridge Drive, the four-to-six-lane stretch Forestbrook drivers use on the way to Conway, started in September 2024. Its contract called for it to be finished by November 30, 2026. WPDE reported on September 2 that SCDOT no longer expects to meet that date and now projects the work will run into spring 2027.

SCDOT spokesperson Tyler Fedor said crews were still installing drainage in the median. Summer limits on lane closures had slowed the work, and those limits lifted after Labor Day, so nighttime lane closures have resumed. SCDOT expects new traffic signals to start going in around February, with the final layer of asphalt in the spring.

Put the two schedules side by side and they overlap:

Season Forestbrook Road (501 to Dick Pond Road) Highway 501 (Highway 544 to Myrtle Ridge Drive)
Fall 2026 Utility relocation; right-of-way acquisition Median drainage; nighttime lane closures back after Labor Day
Winter 2026 County's target for finishing the clearing contract No published milestone
February 2027 No published milestone New traffic signals expected to start going in
Early 2027 Main widening construction expected to start No published milestone
Spring 2027 No published milestone Final asphalt; expected completion
2029 Expected completion Finished

The 501 delay comes from contract changes that WPDE says SCDOT hasn't fully explained. Questions about the original price, the current authorized price and whether the contractor faces penalties are still waiting on answers from the agency. If spring 2027 slips too, the overlap with Forestbrook Road gets longer.

It also isn't the only delay in the county's road program. The Sun News noted that roughly 10 unfinished RIDE III projects, approved by voters in 2016, will now be finished and paid for under RIDE IV, which passed in 2024. Horry County Director of Public Information Thomas Bell told the paper there are "certain things that are out of our control" that can push a schedule back.

How Lane Closures Might Work, and What Isn't Published Yet

Once main construction begins, the big daily question will be how traffic moves through the work zone. In 2025, WBTW reported that the options under consideration included nighttime closures instead of daytime ones, shifting traffic instead of closing the road outright, and limiting lane closures around school hours. Those were planning ideas at the time, not a posted schedule. No closure calendar or set work hours for Forestbrook Road has been published since.

The finished design is clearer at the level of the whole corridor. Horry County describes five lanes, including a center turn lane, plus sidewalks, wider travel lanes and bike and pedestrian facilities along the full stretch between Highway 501 and Dick Pond Road. A center turn lane gives left-turning traffic from side streets and driveways its own space, separate from the through lanes.

What isn't public yet is how the individual intersections will be built. The county's published plans don't say whether the junctions at Highway 501 or at Dick Pond Road will get new signals, added turn lanes or another design. That detail will shape the finished commute more than the lane count, so it's the next document worth watching for from the county.

The Corridor Keeps Building Around the Work

The road schedule hasn't held back new businesses nearby. Forestbrook Commons at 3540 Belle Terre Blvd. has gained a restaurant this year. Angell Bros. Grill moved there from Surfside Beach. The Sun News reported in January that the owners were aiming to open by May 1, 2026, with a larger bar, an expanded menu and an outdoor patio. It's now open from 11 a.m. to 9 p.m. Sunday through Thursday and until 10 p.m. Friday and Saturday.

Dank Burrito is also headed to the same center. WMBF first reported it in February, and the chain's location page still lists the Myrtle Beach site as "Opening Soon," with no date posted. When WMBF covered the Forestbrook Commons announcements, Forestbrook resident Bob Higginbottom told the station he thinks the area has reached "a saturation point." Murrells Inlet resident David McLean said he likes seeing the progress but hopes it doesn't bring too much traffic. The Forestbrook Road widening is the county's answer to that traffic concern. By its own schedule, the answer arrives in 2029.

Planning a sale, a purchase or just the next few years around Forestbrook's road work? Lindsay Jones can walk you through how the Forestbrook Road and Highway 501 timelines line up with the specific streets you're considering, from right-of-way frontage to the side roads that will get a center turn lane. Work With Lindsay.

Work With Lindsay

Lindsay is dedicated to helping you find your dream home and assisting with any selling needs you may have. She values the trust clients place in her and works tirelessly on their behalf to offer attention to detail for each transaction. Contact her today so he can guide you through the buying and selling process.